CASE STUDY: ELECTRICAL CONNECTION TO A NEW BUSINESS PARK IN BEDFORD

Glenmore Business Park in Bedford is a development of 23 business units, including a mix of light industrial warehouses.

The development required a dedicated 800kVA packaged substation with a Low Voltage (LV) network around the site. Each of the 23 units had an individual three-phase cut out.

OUR SOLUTION

* The works progressed very smoothly both on and off-site, resulting in a timely energisation.

* Rock Power Connections revised the proposed High Voltage (HV) cable route to site for ease of road crossing.

* By communicating closely with the developer, we agreed a schedule for the final connections to fall in with the developer’s line of work.

Darren Huxley, Rock’s Project Manager, commented: “The project ran very successfully and was delivered in line with the original design and project plan. A great development to be involved with.”

HOW CAN WE HELP YOU?

With our experience and engineering knowledge, we successfully manage various ICP projects of varying size and scale across the UK.

By trusting Rock Power Connections with your new or upgraded electrical connection, you can rely on us to deliver your engineering solution on time and on budget.

All our customers work closely with their dedicated Rock Power Connections Project Manager to develop a programme of works that fits with their engineering requirements and is flexible to their needs.

We’d be delighted to offer you a free, no obligation, competitive quote for your electrical connection project. Please email Emma on Emma@rockpowerconnections.co.uk, call 01905 456384 or click here to submit your enquiry.