The Challenge

The Kettleworks is an ambitious residential development in Birmingham’s Jewellery Quarter, involving the conversion of the Swan Kettle factory.

In total, there are 292 apartments, each requiring an individually metered supply.

The central location of the project required a temporary road closure in a busy district.

Our Solution

Rock Power Connections installed two 1MVA substations within the development.

We also provided the internal network consisting of 15 Multi Service Distribution Boards (MSDBs) and 292 single phase supplies.

In addition, a separate three-phase supply was installed for a commercial unit.

“Despite the challenging environment, we led the project to success, with a very satisfied client”

Colin Green, Project Manager