The development, which has been built with sustainability, longevity and productivity at its forefront, comprises of 10 units of warehouse space with integrated offices for a wide range of occupiers. Our team were appointed to install Low Voltage main from a new substation to HDCTs housed in GRP enclosure, on a client constructed plinth.

Our solution

  • The installation had already been commenced; which added to the complexity of the install. Careful planning and logical perspective was required to get switchgear delivered on site safely.
  • All previously installed cables were tested with fault-finding equipment. Defected cables were detected and repaired by the team before further works commenced. Despite this setback, the team completed all works before the meters were fitted.

Segre Paro - Rainham

This was a challenging install due to the existing LV network onsite, but by working closely with the developer and main contractor, we were able to compile a unique design which met both the IDNOs design standards and enabled each unit to be individually metered as per the developers requirement.

SEGRO Park is one of the latest connection projects to have successfully been completed by us within a short timeframe.

“The site was energised within the clients specified timescales and was a huge success, and it was great to be involved in such a pioneering development.”