Large power supply to new depot for Quattro UK Ltd

Quattro UK Ltd were setting up a new depot in Southall and the site required a 1MVA electrical supply.

The Challenge

* The project required several redesigns due to planning constraints on the location of the substation.

* The Rock Team liaised with the Council to work out-of-hours in order to minimise disturbance to the local recycling centre.

Our Solution

* The Rock Team installed a HV metred supply in a GRP housing.

* In addition, the Rock Team supplied and installed a privately-owned transformer.

“The clients faced many issues with the construction due to the planning. However, once finalised, Rock were called to site, did a swift installation and met all client’s expectations.”

Rob Davies, Rock’s Project Manager