i54 Business Park

Case study

i54 Business Park

The Challenge

The i54 Business Park in South Staffordshire required a new 33/11kV substation to support its expansion. A number of new businesses were locating on the park including the Jaguar Land Rover engine manufacturing plant.

Rock Solid Solution

This project delivered two new 90MVA, 33/11kV transformers and new 33kV switchgear, protection and control. We also acted as Principal Contractor. In addition, Rock Power Connections also delivered:

• Installation of small power and lighting in control room
• Installation of relay panels, RTUs, multicore cables and wiring
• Installation of Busbars, Circuit Breakers, Disconnectors
• Earthing

“The whole team at Rock Power Connections were excited to work on this high-profile project which would provide a new electricity supply to Jaguar Land Rover’s plant. My team worked efficiently, safely and tirelessly to deliver a state-of-the-art new substation and equipment to site. We’re proud our rock solid solution supported local regional business growth.”

Tim Arnott – Project Manager, Rock Power Connections